Large projects

Welfare building frame, Rotherham

A complete steel-framed welfare building with purlins and cladding rails, drafted, built and erected by our team.

Location
Bramley, Rotherham (S66)
Client
Property company
Steel
About 25 tonnes, plus 600 m of purlins
Our work
Drafting, 3D model, fabrication, delivery, installation
Programme
Drafted November 2020, installed February to March 2021

The job

A new welfare building for an industrial site in South Yorkshire, framed in steel with cold-rolled purlins and cladding rails.

What we did

We drafted and modelled the frame and cold-rolled secondary steel, fabricated around 25 tonnes of structural steel, and supplied about 600 metres of purlins and 660 metres of cladding rails.

On site

Our team travelled up and erected the building over about three weeks with a crane, a mini crane and a MEWP, setting holding-down bolts in resin.